Bids for the medical facility addition at Buckeye Career Center were awarded at the Aug. 20 meeting of the Buckeye Career Center Board of Education.

They included Massillon Construction addition bid of $4,145,429, Flickinger Piping Co. of $774,500 for air handler replacements and Martin Public Seating of $104,596.71 for furnishing the medical facility.

The board also did the following:

—Approved a 4% administrative raise for the next three years, beginning with the 2024-25 year, which was included in the $2,800,000 4% base increase approved at a previous meeting that included a three-year contract with a 4% wage hike with the Buckeye Education Association.

—Approved various personnel recommendations.

—Set the next meeting for Sept. 17 at 7 p.m.